The Paperwork Behind The HOA Gap: Reading A Fort Lee High-Rise Resale Package In 2026

July 23, 2026

Two Fort Lee units go under contract the same week. Same tower silhouette from the balcony, same George Washington Bridge sightline, same square footage on the floor plan. One monthly HOA is roughly $1,100. The other is closer to $1,700. The listing photos will not tell you why, and neither will the amenity list, because both buildings have a pool, a doorman, and a garage.

The answer sits in two documents that are only now becoming standard in Fort Lee resale packages. One is a structural engineer's report that most covered buildings had to complete by January 8, 2026. The other is a bold-font funding notice that a seller is required to hand a buyer before contract execution if the association elected a specific reserve option in the last budget cycle. If you are buying or selling in a Fort Lee tower this year, the resale package is doing more work than it did in 2023, and reading it correctly is where the money is.

The document that should be in every Fort Lee resale package this summer

New Jersey's Structural Integrity Law, P.L. 2023, c.214, applies to "covered buildings," which the statute defines as residential condominium or cooperative buildings whose primary load bearing system is concrete, masonry, steel, or a hybrid structure, including heavy timber and buildings with podium decks. Standard wood-frame construction is excluded. In Fort Lee, that definition catches essentially every high-rise on the ridge, including The Palisades at 100 Old Palisade Road, a 29-story tower with 538 units completed in 2002, River Ridge next door at 31 stories from 1984, Atrium Palace at 19 stories from 1989, and Royal Buckingham at 22 stories from 1994.

For any covered building whose certificate of occupancy predated January 8, 2009, the initial structural inspection was required on or before January 8, 2026. A licensed New Jersey engineer evaluates the primary load bearing system, and the report has to specify any required maintenance or repairs, when the next inspection must occur, and follow-up cadence. The follow-up window is at most 10 years, unless the building is more than 20 years old, in which case it drops to 5 years, or within 60 days of any observable damage to the primary load bearing system.

Practically, that means the resale package for a Fort Lee tower built before 2009 should now contain:

  • The initial structural inspection report itself, prepared per the American Society of Civil Engineers protocol.
  • Any repair timeline the engineer set.
  • The date the next inspection is due, which for buildings over 20 years is a five-year clock.

If the seller cannot produce it, the association either has not complied, has an extension tied to a phased inspection, or has not yet forwarded documents to the unit owner. Any of those is worth flagging to your attorney before attorney review closes.

The 20-point bold notice most buyers have never seen

On August 21, 2025, Governor Murphy signed S3992, enacted as P.L. 2025, c.132, which modifies capital reserve funding requirements for planned real estate developments. The amendment kept S2760's inspection framework intact and rewrote the funding rules underneath it.

Two things now define an "adequately funded" association in New Jersey. First, every reserve study must include a 30-year baseline funding plan in which the projected reserve balance never falls below zero. Second, an existing association may temporarily fund at 85 percent of its selected plan for up to five fiscal years, but only if it complies with a specific disclosure requirement.

That disclosure is where a buyer's diligence lives. If an association elects the 85 percent option, it must notify unit owners in 20-point bold font, and the notice must state the funding level, the anticipated year of a special assessment or loan, and the amount. The seller has to give the same notice to the buyer before contract execution. New associations formed after August 21, 2025 do not get the 85 percent option at all and must fully fund from inception.

If you are the buyer, you are looking for one of two things:

Either a resale certificate stating the association is funding at baseline or above with no shortfall projected, or a 20-point bold-font notice naming a year and a dollar figure for the next assessment or loan.

Either answer is workable. Silence is not. A quiet resale packet in a pre-2009 tower is more likely to be an incomplete file than a clean building.

Why two identical-view towers now quote different HOAs

Building vintage, primary load bearing material, and funding election together explain most of the HOA spread across Fort Lee towers. Here is how the variables stack up in the local stock:

Building profile C.O. year Initial inspection status Structural clock
Tower A, concrete/steel, pre-1985 Before 2009 Required by Jan 8, 2026 5-year re-inspection cadence, 60-day rule on observable damage
Tower B, concrete/steel, mid-1990s Before 2009 Required by Jan 8, 2026 5-year cadence once past the 20-year mark
Tower C, concrete/steel, early 2000s Before 2009 Required by Jan 8, 2026 10-year cadence until 20 years old
Tower D, concrete/steel, 2015 delivery After 2009 Due within one year of 15th anniversary of C.O. 10-year cadence to start

A building matching Tower A's profile has more mandatory scrutiny of its primary load bearing system on a tighter clock. If its reserve study also shows a shortfall, the board has three choices under S3992: raise contributions to reach baseline, elect the 85 percent path with the bold-font notice, or plan for a special assessment or loan. Each choice touches monthly HOA in a different way, and each shows up in the resale package as a different piece of paper.

The Tower C profile, which fits The Palisades at 100 Old Palisade Road, sits in a different position: it still owed an initial structural inspection by January 8, 2026 because the C.O. was before 2009, but its re-inspection cadence stays at 10 years until 2022's twentieth anniversary of its 2002 completion. Rate of scrutiny bends the cost curve.

What to ask before you sign

For a buyer in Fort Lee this summer, five questions surface most of what the statute changed:

  1. Is the building a "covered building" under P.L. 2023, c.214, and if so, when was the initial structural inspection completed and by which licensed engineer?
  2. What did the report say about the primary load bearing system, and what repair timeline did the engineer set?
  3. When is the next inspection scheduled?
  4. Which funding plan did the board adopt under S3992, baseline or the temporary 85 percent option?
  5. If the 85 percent option was elected, produce the 20-point bold-font notice with the projected year and amount of the next assessment or loan.

For a seller, the same list runs in reverse. If you are listing in a pre-2009 tower and your association has not yet produced the inspection report or a compliant funding notice, that gap will be discovered during attorney review. The offer that survives is the one where the buyer's attorney and lender have already seen the paper.

One local wrinkle worth tying in

The state law is not the only compliance item touching Fort Lee towers this year. Fort Lee Borough adopted Ordinance 2025-17 requiring parking-structure inspections by a New Jersey licensed professional engineer. Almost every high-rise in the borough has an attached or below-grade garage that qualifies, and the resulting engineer's report becomes another line item in the resource pool that boards fund out of reserves. For buyers modeling the next five years of HOA, that ordinance sits alongside the state inspection cost as a recurring, non-optional professional fee.

Short FAQ

Does S3992 apply to co-ops as well as condos? Yes. The Structural Integrity Law and its 2025 amendment apply to community associations governed by the Planned Real Estate Development Full Disclosure Act, which includes both condominiums and cooperatives with a primary load bearing system meeting the covered-building definition. Fort Lee's stock includes both formats.

If a building missed the January 8, 2026 inspection deadline, is my closing affected? The closing itself is not automatically blocked, but lenders and insurers are increasingly asking for evidence of compliance. Non-compliance can complicate a lender's condo review, particularly under stricter secondary-market condo eligibility rules. Ask the association's manager for a written status update and share it with your lender before the appraisal contingency clears.

Can the board waive the 20-point bold-font notice if the shortfall is small? No. The disclosure runs with the election. If the association is funding at 85 percent of its selected reserve plan, the notice format and content are set by statute, and the seller's obligation to deliver it to a buyer before contract execution is independent of the size of any anticipated assessment.

Is the initial structural inspection the same thing as a reserve study? No. The structural inspection is an engineer's assessment of the primary load bearing system. The reserve study is a 30-year financial projection of common-element repair and replacement funding, prepared by a licensed engineer or a credentialed reserve specialist. A well-run association has both, and both should show up in the resale package.


Reading a Fort Lee resale package the way it reads in 2026 takes an agent who is comfortable with an engineer's report and a reserve study, not only a comparable-sales sheet. If you are preparing to list a unit in one of the ridge towers or you are the buyer trying to price the paperwork behind two similar quotes, Sara Shin Select can walk the file with you before you sign. Let's connect.

Work With Sara

Whether it’s a home, warehouse, or medical building, Sara knows how to showcase properties at their highest value.